MS Project - Settings
Each one of you might be using a different setting for MS Project 2013. To ensure the results are not different from what is shown in this tutorials, ensure the settings as follows. Remember all these are the default settings you will have when you first install MS Project 2013 on your computer.
Step 1 − File → Options → General tab → Project view → Default view.

Select Gantt with Timeline from the dropdown box.

Step 2 − File → Options → Display tab → Show Indicators and Options Buttons For.
Check all options.

Step 3 − File → Options → Schedule tab → Schedule → Show Assignment Units.
Choose percentage from the dropdown box.

Step 4 − File → Options → Schedule tab → Calculation → Calculate Project after Each Edit.
Check the On button.

Step 5 − File → Options → Save tab → Save projects → Save Files In this format.
Select Project (*.mpp).

Step 6 − File → Options → Advanced tab → Edit.
Check all options.

Step 7 − File → Options → Advanced tab → Display → Show Status Bar → Show Scroll Bar.
Both options, Status Bar and Scroll Bar should be checked.

Step 8 Resources → Level → Leveling Options → Leveling Calculations.
Set to manual.


Step 9 − Resources → Level → Leveling Options → Leveling calculations → Look for Overallocations.
Select Day By Day from dropdown box.