Following quiz provides Multiple Choice Questions (MCQs) related to SAP PM. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Answer : E

Explanation

Key functions as part of Plant Maintenance −

  • Inspection and Notifications
  • Corrective and Preventive Maintenance
  • Breakdown Maintenance
  • Repair
  • Other measures - charactertics and Key Figures

Answer : C

Explanation

In SAP PM, when there is a malfunction occurs for any of the equipment which requires a response from Maintenance team. The process of correcting this situation is known as Breakdown maintenance.

Q 3 - What is the order type to perform Preventive Maintenance in Plant Maintenance?

A - PM01

B - PM02

C - PM03

D - PM04

Answer : C

Explanation

In SAP system, PM01 is the order type to perform Corrective maintenance and PM03 is for performing Preventive maintenance.

Q 4 - In which of the component, capacity of work centers are shown in graphical manner and you can use new planning tree for displaying capacity view of planning board?

A - MEB

B - Log Book

C - Outline agreement

D - Service Contract

Answer : A

Explanation

Using MEB in SAP Plant Maintenance, you can easily manage the maintenance planning consists of work packages. The capacity of work centers are shown in graphical manner and you can use new planning tree for displaying capacity view of planning board.

Q 5 - In SAP Plant Maintenance, Refurbishment process is integrated with MM, CP and PS?

A - True

B - False

Answer : A

Q 6 - To better manage and monitor Plant Maintenance process in Financial Management, you can integrate Plant Maintenance (PM) and Funds Management (FM)?

A - True

B - False

Answer : A

Q 8 - Which of the time based scheduling allows you to perform Maintenance strategy every 30 working days?

A - Time Based

B - Time Based by Key date

C - Time Based by factory calendar

D - All of the above

Answer : C

Explanation

Time-based (for example, every 30 days)

Time-based by key date (for example, every 30 days on the 30th day of the month)

Time-based by factory calendar (for example, every 30 working days)

Q 9 - A Maintenance Plan must contain atleast on of Maintenance Items?

A - True

B - False

Answer : A

Q 10 - A Repair is known as- all measures which restore the ideal condition of a technical system?

A - True

B - False

Answer : A